Velocity is the correct answer. To plan how much work can be done in the next release, agile typically uses the velocity trend over the last several iterations. Gathering groups of user stories or summing story points factor into the velocity
in which iterations are completed. User stories, story points, and affinity estimating are incorrect responses because they are not used to determine the amount of work to be done in the next release of the project.