Concept:Use the given efficiency ratios to find the total work, then compute the remaining work and the required time.
Explanation:Let the efficiency of B be
1 unit per day.
A is 25% more efficient than B, so efficiency of A is
1+41​=45​ units per day.
C is 25% less efficient than B, so efficiency of C is
1−41​=43​ units per day.
Combined efficiency of A, B and C is
45​+1+43​=3 units per day.
All three together finish the work in 24 days, so total work is
3×24=72 units.
Efficiency of B and C together is
1+43​=47​ units per day.
Work done by B and C in 32 days is
47​×32=56 units.
Remaining work is
72−56=16 units.
With double efficiency, B works at
2×1=2 units per day.
Time needed by B alone is
216​=8 days.
Answer:8 days, i.e., Option A.