No. of bricks = (volume of brick work / volume of one brick with mortar)
Volume of one brick (without mortar)
= .19×.09×.09 = 0.001539 m
3 since thickness of mortar = 10 mm (0.01 m)
Volume of brick with mortar
= (0.19 + 0.01) × (0.09 + 0.1) × (0.09 + 0.1)
= 0.2 × 0.1 × 0.1 = 0.002 m
3 Therefore, Number of bricks =
=
500consider the percentage of waste as 15 %Total no. of bricks
=500+=575Now, Calculation for quantity of mortarSince we need 500 no of bricks
Volume occupied by bricks = No of bricks × volume of one brick
Volume of bricks = 500 × 0.001539 = 0.7695 m
3Volume of mortar = Volume of BRICK WORK – Volume of BRICKS
therefore,
Volume of Mortar = 1.0 – 0.7695 = 0.2305 m3The approximate proportion of dry volume of cement mortar required for brick work = 1.33 × 0.2305 = 0.3065 m
3 (Approx 33% increment due to volume shrink after water)