The shuttering of a hall measuring 4 m × 5 m, can be removed after 7 days. The time taken for removing shuttering depends on span of beam For example- ● 7 days for beam formwork. ● 14 days for slab of span 4.6m & more ● 21 days for bottom beam over 6m span