Opportunity and risk generally remain high during the concept and planning phases. However, the amount at stake remains low because of the relatively low level of investment up to that point. During project implementation and closeout, however, risk falls to lower levels as remaining unknowns are translated into knowns. At the same time, the amount at stake rises steadily as the necessary resources are invested to complete the project.