The correct answer is that previous iterations include all variables of development. The other answers are incorrect: although consistent team membership is valuable, changes in members shouldn’t change the iteration’s velocity; since
not all user stories are equally complex, the same number of stories can’t be used to predict future progress; each iteration has different tasks.