Having a single document manage the project requirements is a fundamental agile practice. One information source regarding the work that needs to be done allows itself to communicate effectively and provides a visual of scope progress
and project status. The other responses are incorrect because the purpose of the backlog process isn’t to bypass a story, determine how long the project will take, or how much the project will cost.