Concept:Work done is measured in total person-hours, and since all three have equal ability, their hourly work rates are the same.Explanation:Third person alone works for 29 days at 16 hours per day.So total work =16×29=464 person-hours.Total work done by all three individually is also the sum of their total working hours.Thus, m×m+n×n+16×16=464.This gives m2+n2+256=464, so m2+n2=208.The integer pair satisfying this is (12,8), since 122+82=144+64=208.Working together, their combined rate per day is m+n+16=12+8+16=36 person-hours per day.Time required =36464​≈12.89 days.So they can complete the work in about 13 days.Answer:Option B: 13 days.