Concept:Convert all workers into equivalent men using the given relation of work capacities, then compare total men-hours required for the two pieces of work.
Explanation:Given that 15 men, 24 women, and 36 boys do the same work in the same time, their capacities are equivalent:
15 men
=24 women
=36 boys.
First, express 12 women and 6 boys in terms of men.
1 woman
=2415​=85​ men.
So,
12 women
=12×85​=215​ men.
1 boy
=3615​=125​ men.
So,
6 boys
=6×125​=25​ men.
Total already working
=215​+25​=10 men.
Now, the original work is done by 15 men in 12 days, working 8 hours per day.
Total man-hours for original work
=15×12×8.
The new work is
241​=49​ times as large.
Let the total number of men required for the new work be
x.
Since the new work is done in 30 days working 6 hours per day:
x×30×6=49​×15×12×8x=49​×30×615×12×8​=49​×8=18Total man-equivalent required
=18 men.
Extra men needed
=18−10=8.
Answer:8 men must be associated. Correct option: C.