Concept:Total work output must be at least 24 units per day.Explanation:Let x be the number of experienced persons and y be the number of A persons.Each experienced person does 6 units, each A person does 2 units.Total daily output = 6x+2y.The condition "at least 24 units" means 6x+2y≥24.Answer:6x+2y≥24 (Option C)