Directions (51–55) : Study the graph and table carefully to answer the following question. Five persons A, B, C, D and E are employed to do a job X.
Graph shows the data regarding the time taken by five persons to complete the job X
Job X
Time of doing by different persons
PersonTime (in days)A—B2C4D4E—\begin{array}{lc} \text{Person} & \text{Time (in days)} \\ \text{A} & \text{---} \\ \text{B} & 2 \\ \text{C} & 4 \\ \text{D} & 4 \\ \text{E} & \text{---} \end{array}
Note 1 : All persons worked on the job X for whole number of days.
Note 2 : Two jobs Y and Z are similar to job X and require same effort as required by job X.