Question Numbers: 62-63 For a particular project, eight activities are to be carried out. Their relationships with other activities and expected durations are mentioned in the table below.Activity Predecessors Duration (days)
| Activity | Predecessors | Duration(days) |
| A | - | 3 |
| B | A | 4 |
| C | A | 5 |
| D | A | 4 |
| E | B | 2 |
| F | D | 9 |
| G | C, E | 6 |
| H | F, G | 2 |