GIVEN: Saral, Ravi and Karan alone takes 10, 12 and 15 days, respectively to complete a task. FORMULA USED: Time = Work / Efficiency CALCULATION: Saral, Ravi and Karan alone takes 10, 12 and 15 days Efficiency of Saral =101​ units Efficiency of Ravi =121​ units Efficiency of Karan =151​ units Suppose the number of days taken to complete the task is ‘a’. Saral worked for 2 days, Ravi worked for (a - 3) days and Karan worked for a days. Now, 102​+12a−3​+15a​=1⇒51​+12a​−41​+15a​=1⇒203a​=1+201​⇒203a​=2021​ ⇒ a = 7 ∴ Number of days taken to complete the task = 7 days