Question : 1 of 29
Marks: +1, -0
'RAVL' is a company manufacturing LED bulbs. To ensure efficiency in production, the workers are given monthly targets. For the month of October 2025, the workers were given a target to produce 8,000 bulbs. At the end of the month, it was found that actual production was only 6,000 bulbs. After investigation, it was found that the target was not met due to shortage of trained workers. To resolve the problem, the Production Manager arranged training programmes for workers and also hired additional workers.
Which step of the controlling process was followed by the Production Manager to resolve the problem of shortage of trained workers ?
[CBSE 2026 66/3/3]
Solution:  
Concept: Steps in the controlling process: (1) setting performance standards, (2) measurement of actual performance, (3) comparing actual performance with standards, (4) analysing deviations, (5) taking corrective action.
Explanation: The target of 8,000 bulbs is the standard, 6,000 bulbs is the measured actual performance, and finding the shortfall and its cause (shortage of trained workers) is comparison and analysis of deviation. The question asks about the step used to resolve the problem: "arranged training programmes for workers and also hired additional workers". Removing the cause of the deviation is taking corrective action.
Answer:
Option D (Taking corrective action)